Mendocino County battery storage rules
Projects go through general utility, energy or use-permit rules.
- Key rules
- Title 20 (Zoning) has no energy storage provisions (GoCodebook copy, Oct 2026 edition). Solar farms go through a Major Use Permit as Major Impact Services and Utilities (Hooper, U_2023-0008, July 2024).
- Pending action
- Data center moratorium (not BESS): urgency ordinance on the Aug 17, 2026 agenda and a 22-month-15-day extension on the Sept 22, 2026 agenda; outcomes not checked.
- Projects
- Form Energy's East Road Storage (5 MW/500 MWh iron-air demonstration, CEC as lead agency) approved Dec 13, 2023. CAISO queue: no storage entries.
- Sources
A brief on Mendocino County
A brief covers the rules in force, pending changes, every project proposed in the last five years, how the supervisors voted and the next hearing date, with every claim sourced.
Research from public records, not legal advice. How this table is built.