Siting Desk

5 of 58 California counties have battery storage rules in force

Four more are drafting rules and San Benito has paused approvals. Every row links its source: county codes, agendas, CEQA filings and the CAISO queue, checked Nov 15 and 16, 2026.

All 58 counties

Showing all 58 counties.

CountyKey rulesPending actionProjectsSourcesChecked
AlamedaNo battery-specific rulesNo zoning ordinance allows standalone battery storage, per the Planning Director's Dec 1, 2025 briefing to the Board's Transportation/Planning Committee. East County land also falls under Measure D.Planning staff briefed the committee on BESS Dec 1, 2025; no ordinance hearing found.Opt-in: Potentia-Viridi (Clearway, 400 MW/3,200 MWh) approved by the CEC May 26, 2026; Viracocha Hill (Ignis, 90.7 MW/362.8 MWh; 25-OPT-01) under review. CAISO files Potentia-Viridi under San Joaquin County. CAISO queue: 5 active storage entries (1,337 MW), incl. Espresso, Spectrum Energy Storage, Zorin Storage; 1 completed.Alameda County Board Transportation/Planning Committee minutes, Dec 1, 2025Nov 15, 2026
AlpineNo battery-specific rulesTitle 18 (Zoning) has no energy storage provisions (GoCodebook copy, Oct 2026 edition).None found in CEQAnet or news searches.No BESS projects in CEQAnet since 2023. CAISO queue: no storage entries.GoCodebook: Alpine County Code, Oct 2026 editionNov 15, 2026
AmadorNo battery-specific rulesTitle 19 (Zoning) has no energy storage provisions (GoCodebook copy, Oct 2026 edition).None found in CEQAnet or news searches.No BESS projects in CEQAnet since 2023. CAISO queue: no storage entries.GoCodebook: Amador County Code, Oct 2026 editionNov 15, 2026
ButteNo battery-specific rulesChapter 24 (Zoning) has no energy storage provisions (GoCodebook copy, Oct 2026 edition). Solar plus storage goes through a Conditional Use Permit (La Porte Road, UP23-0005).None found in CEQAnet or news searches.La Porte Road Solar + Battery Energy Storage (3 MW, 17 acres, UP23-0005): MND Feb 9, 2024. CAISO queue: no storage entries.GoCodebook: Butte County Code, Oct 2026 editionCEQAnet: La Porte Road Solar + BESSNov 15, 2026
CalaverasNo battery-specific rulesTitle 17 (Zoning) has no energy storage provisions (GoCodebook copy, Oct 2026 edition). BESS goes through a Conditional Use Permit (Double Springs, CUP 2024-086).None found in CEQAnet or news searches.Double Springs Energy Storage (15.2-acre lithium-ion BESS): MND Dec 3, 2025; CUP 2024-086 approved Aug 13, 2026; a second NOD followed Sept 14, 2026. CAISO queue: 1 active storage entry (101 MW), incl. Double Springs Energy Storage.GoCodebook: Calaveras County Code, Oct 2026 editionCEQAnet: Double Springs Energy StorageNov 15, 2026
ColusaNo battery-specific rulesChapter 44 (Zoning Code) has no energy storage provisions (GoCodebook copy, Oct 2026 edition). Saloon BESS got a Major Use Permit and franchise agreement (PD-25-6).None found in CEQAnet or news searches.Saloon BESS (up to 150 MW, near PG&E's Cortina substation, PD-25-6) approved Nov 18, 2025. Janus Solar and Battery Storage use permit approved Feb 25, 2025. CAISO queue: 2 active storage entries (230 MW), incl. Janus, Saloon Energy Storage.GoCodebook: Colusa County Code, Oct 2026 editionCEQAnet: Saloon BESSCEQAnet: Janus Solar and Battery StorageNov 15, 2026
Contra CostaNo battery-specific rulesTitle 8 (Zoning) has no energy storage provisions (GoCodebook copy, Oct 2026 edition). Small solar plus storage goes through a Land Use Permit (Ranch Sereno, CDLP22-02036).None found in CEQAnet or news searches.Opson Solar (Byron, 10 MWh BESS, CDLP25-02033): MND posted Oct 8, 2026. Hubbard Farming and Forestry Clean Power (6.6 MW solar with storage) went to the Byron advisory council Sept 2025. CAISO queue: 5 active storage entries (1,601 MW), incl. Allegheny Energy Storage, Black Diamond ES2, Delilah Energy Storage, Harmony Storage 2; 1 completed.GoCodebook: Contra Costa County Code, Oct 2026 editionCEQAnet: Opson SolarNov 15, 2026
Del NorteNo battery-specific rulesTitle 20 (Zoning) and Title 21 (Coastal Zoning) have no energy storage provisions (GoCodebook copy, Oct 2026 edition).None found in CEQAnet or news searches.No BESS projects in CEQAnet since 2023. Outside CAISO (Pacific Power territory). CAISO queue: no storage entries.GoCodebook: Del Norte County Code, Oct 2026 editionNov 15, 2026
El DoradoNo battery-specific rulesTitle 130 (Zoning) has no energy storage provisions (GoCodebook copy, Oct 2026 edition). BESS goes through a Conditional Use Permit: Stella Battery Storage (CUP22-0010) cleared the Zoning Administrator June 5, 2024.None found in CEQAnet or news searches.Stella (CUP22-0010) and Fuji (CUP22-0011) battery storage, 5 MW/20 MWh each. Fuji went to the Planning Commission July 2025; outcome not checked. CAISO queue: no storage entries.GoCodebook: El Dorado County Code, Oct 2026 editionCEQAnet: Stella Battery Energy StorageNov 15, 2026
FresnoNo battery-specific rulesThe Zoning Ordinance (Feb 2024 edition) contains no 'battery' or 'energy storage' text. How standalone BESS are classified needs a call to the planning desk.None found.Opt-in: Darden Clean Energy (Intersect Power, 1,150 MW solar, 1,150 MW/4,600 MWh), approved by the CEC June 11, 2025; under construction. CAISO queue: 26 active storage entries (4,566 MW), incl. Apache Storage, Ciervo Mountain Hybrid, Heartland 1; 3 completed.Fresno County Zoning Ordinance (Feb 2024 edition, PDF)Nov 15, 2026
GlennNo battery-specific rulesTitle 15 (Unified Development Code) has no energy storage provisions (GoCodebook copy, Oct 2026 edition).None found in CEQAnet or news searches.No BESS projects in CEQAnet since 2023. CAISO queue: no storage entries.GoCodebook: Glenn County Code, Oct 2026 editionNov 15, 2026
HumboldtNo battery-specific rulesTitle III (Land Use and Development) has no energy storage provisions (GoCodebook copy, Oct 2026 edition).Data center moratorium (not BESS): 45-day ordinance on the Sept 2026 agenda and a 10-month-15-day extension on the Oct 20, 2026 agenda; outcomes not checked.Foster Clean Power solar and storage (RCEA) got a sign permit Apr 2026. CAISO queue: no storage entries.GoCodebook: Humboldt County Code, Oct 2026 editionNov 15, 2026
ImperialNo battery-specific rulesBESS approved project by project through Conditional Use Permits, often with a general plan amendment and zone change (Border BESS: CUP24-0027, GPA25-0001, ZC25-0001). No BESS-specific code section found.Border BESS (Apex Energy Solutions) initial study, Mar 2026. Titan II BESS (40 MW) EIR started June 2026.Opt-in: Perkins Renewable Energy (Intersect Power, 1,150 MW solar, 4,600 MWh); status not checked. Seville 4 and 5 solar and storage approved Jan 27, 2026. Many projects sit in IID territory, outside the CAISO queue. CAISO queue: 5 active storage entries (1,814 MW), incl. LeConte Energy Storage, Umbriel; 2 completed.Imperial County ICPDS: Border BESS hearing package (Mar 12, 2026)Nov 15, 2026
InyoNo battery-specific rulesTitle 18 (Zoning) and Title 21 (Renewable Energy Ordinance, 2010) have no energy storage provisions (GoCodebook copy, Oct 2026 edition). Title 21 covers solar, wind and transmission permits.ZTA 2026-01, which rewrites the renewable energy design standards in Sec. 21.20.020, went to the Planning Commission Sept 23, 2026; Board action not checked.No BESS projects in CEQAnet since 2023. CAISO queue: 2 active storage entries (765 MW), incl. Calvada Springs Solar, Sunbaked Solar.GoCodebook: Inyo County Code, Oct 2026 editionInyo Planning Commission staff report, ZTA 2026-01Nov 15, 2026
KernNo battery-specific rulesBESS approved by Conditional Use Permit in the A (Exclusive Agriculture) district under Zoning Ordinance Sec. 19.12.030.G, alone or with solar. No BESS-specific standards found.Euismod Energy Storage (1,150 MW/9,200 MWh standalone, Rosamond area): EIR started Dec 2025.Buttonbush Solar and Storage (Avantus, 2 GW solar, 16 GWh) approved by the Board Mar 24, 2026. Discovery Solar PV and Storage (Terra-Gen, 1,400 MW solar, 8 GWh) approved by the Board June 16, 2026. Galaxy Solar PV and Storage (Terra-Gen, 600 MW solar, 4 GWh) approved by the Board Sept 29, 2026. CAISO queue: 37 active storage entries (8,196 MW), the most of any county; 15 completed.CEQAnet: Buttonbush Solar and Storage Project (cites Sec. 19.12.030.G)CEQAnet: Discovery Solar NOD, June 18, 2026PV Tech: Galaxy approval, Sept 30, 2026Nov 15, 2026
KingsOrdinance in forceDevelopment Code Table 4-1 lists electrical energy storage facilities as a Conditional Use Permit use in AG-20, AG-40 and AX; they are not permitted in AL-10 and must sit within 1 mile of an existing public utility substation. No other BESS standards found (GoCodebook copy, June 2026 edition).Rex Solaire Solar and Storage (CUP 25-04): EIR notice of preparation reissued June 29, 2026.Outlaw Energy Storage (esVolta, 110 MW, CUP 23-06, AG-20): MND Oct 2024. Cherry BESS (CUP 26-01, split from Westlands Cherry Solar) approved Apr 6, 2026. Westlands VI Solar (250 MW solar, 250 MW battery, CUP 26-02) amended Sept 14, 2026. CAISO queue: 8 active storage entries (1,814 MW), incl. Air Station 1, American Kings Solar, Daylight, Kettleman Solar Project; 5 completed.GoCodebook: Kings County Development Code, June 2026 editionCEQAnet: Outlaw Energy StorageCEQAnet: Cherry BESS and Westlands VINov 15, 2026
LakeNo battery-specific rulesChapter 21 (Zoning) has no energy storage provisions (GoCodebook copy, Oct 2026 edition).None found in CEQAnet or news searches.No county BESS projects in CEQAnet since 2023. CAISO queue: 1 active storage entry (47 MW), incl. Bottle Rock Power; 2 completed.GoCodebook: Lake County Code, Oct 2026 editionNov 15, 2026
LassenNo battery-specific rulesTitle 18 (Zoning) has no energy storage provisions (GoCodebook copy, Oct 2026 edition).None found in CEQAnet or news searches.CAISO queue: no storage entries.GoCodebook: Lassen County Code, Oct 2026 editionNov 15, 2026
Los AngelesDraft rulesTitle 22 has no BESS use category yet. Storage has been approved as an accessory use to utility-scale solar by CUP, which opponents contested in a Board appeal (Jan to Feb 2026).Renewable Energy Ordinance Update adds BESS uses and standards: public review draft July 2026; Program EIR notice of preparation Aug 3, 2026 (comments closed Sept 17, 2026); hearings not scheduled.Opt-in: Prairie Song Reliability (1,150 MW/9,200 MWh, Acton; 25-OPT-02), under review. CAISO queue: 21 active storage entries (6,755 MW), incl. Avocet Storage, Commerce Energy Storage, Dorian Storage.LA County Planning: REO Update public review draft (July 2026)Nov 15, 2026
MaderaNo battery-specific rulesTitle 18 (Zoning) has no energy storage provisions (GoCodebook copy, Oct 2026 edition). BESS goes through a Conditional Use Permit (New Leaf Energy, CUP 2022-016).None found in CEQAnet or news searches.New Leaf Energy BESS (200 MW on 16 of 35 acres, CUP 2022-016) approved Sept 5, 2023. CAISO queue: 1 active storage entry (203 MW), incl. Lotus Solar 2.GoCodebook: Madera County Code, Oct 2026 editionCEQAnet: New Leaf Energy CUP 2022-016Nov 15, 2026
MarinNo battery-specific rulesTitle 22 (Development Code) and Title 20 (Coastal Zoning) have no grid-scale storage provisions; Chapter 22.20 lists home battery units among features that may project into required setbacks (GoCodebook copy, Oct 2026 edition).None found in CEQAnet or news searches.No county BESS projects in CEQAnet since 2023. CAISO queue: no storage entries.GoCodebook: Marin County Code, Oct 2026 editionNov 15, 2026
MariposaNo battery-specific rulesZoning Code (Title 17) has no energy storage provisions (GoCodebook copy, June 2026 edition).None found in CEQAnet or news searches.No BESS projects in CEQAnet since 2023. CAISO queue: no storage entries.GoCodebook: Mariposa County Zoning Code, June 2026 editionNov 15, 2026
MendocinoNo battery-specific rulesTitle 20 (Zoning) has no energy storage provisions (GoCodebook copy, Oct 2026 edition). Solar farms go through a Major Use Permit as Major Impact Services and Utilities (Hooper, U_2023-0008, July 2024).Data center moratorium (not BESS): urgency ordinance on the Aug 17, 2026 agenda and a 22-month-15-day extension on the Sept 22, 2026 agenda; outcomes not checked.Form Energy's East Road Storage (5 MW/500 MWh iron-air demonstration, CEC as lead agency) approved Dec 13, 2023. CAISO queue: no storage entries.GoCodebook: Mendocino County Code, Oct 2026 editionCEQAnet: East Road StorageNov 15, 2026
MercedNo battery-specific rulesTitle 18 (Zoning) has no energy storage provisions (GoCodebook copy, Oct 2026 edition). BESS goes through a Use Permit in agricultural zones: 100 Tower Road (A-1) and Zeta Solar and BESS (CUP22-015, A-2).None found in CEQAnet or news searches.100 Tower Road 252 MW BESS beside PG&E's Wilson substation approved Oct 23, 2024. Zeta Solar and BESS (Longroad, south of Los Banos): Planning Commission Feb 26, 2025; solar benefits agreement NOD Apr 9, 2025. Spikes Peak Solar EIR started June 2025. CAISO queue: 9 active storage entries (2,258 MW), incl. Australis, Cougar Storage, Gonzaga Hybrid, Las Camas 1.GoCodebook: Merced County Code, Oct 2026 editionCEQAnet: 100 Tower Road BESSCEQAnet: Zeta Solar and BESSNov 15, 2026
ModocNo battery-specific rulesTitle 18 (Zoning) has no energy storage provisions (GoCodebook copy, Oct 2026 edition).None found in CEQAnet or news searches.No BESS projects in CEQAnet since 2023. CAISO queue: no storage entries.GoCodebook: Modoc County Code, Oct 2026 editionNov 15, 2026
MonoNo battery-specific rulesZoning Code has no energy storage provisions (GoCodebook copy, June 2026 edition).None found in CEQAnet or news searches.No BESS projects in CEQAnet since 2023. CAISO queue: no storage entries.GoCodebook: Mono County Zoning Code, June 2026 editionNov 15, 2026
MontereyDraft rulesNo BESS-specific zoning rules yet. On Nov 18, 2025 the Board declined a moratorium (Referral 2025.15) and told staff to draft an ordinance with a consultant. The local emergency for the Moss Landing fire is renewed every 60 days.BESS Ordinance REF260006: community outreach and drafting since spring 2026; no draft released and no hearing date posted.Moss Landing (Vistra Moss 300 burned Jan 16, 2025). CAISO queue: 3 active storage entries (1,664 MW), incl. Irving Storage, Holman, El Rey Power Bank; 4 completed.Monterey County: BESS Ordinance REF260006 page; Board report PAR 25-018 (Nov 18, 2025)Nov 15, 2026
NapaNo battery-specific rulesTitle 18 (Zoning) has no energy storage provisions. A fire code amendment (Sec. 15.32.117, Ord. 1516, Dec 9, 2025) covers home ESS in R-3 and R-4 occupancies only (GoCodebook copy, Oct 2026 edition).None found in CEQAnet or news searches.Energy Vault's Calistoga Resiliency Center (hybrid storage) briefed the county Climate Action Committee June 2025. CAISO queue: no storage entries.GoCodebook: Napa County Code, Oct 2026 editionNov 15, 2026
NevadaNo battery-specific rulesTitle 12 (Zoning Regulations) has no energy storage provisions; the county fire safety standards mention BESS only as an electrical power source (GoCodebook copy, Oct 2026 edition).None found in CEQAnet or news searches.No county BESS projects in CEQAnet since 2023. CAISO queue: no storage entries.GoCodebook: Nevada County Code, Oct 2026 editionNov 15, 2026
OrangeOrdinance in forceOrd. 25-017, Sec. 7-9-122 (effective Dec 4, 2025): Use Permit from the Planning Commission; no site on a parcel in a VHFHSZ; 100 ft from community buildings and homes unless justified; 6 ft non-scalable wall; enclosures 15 ft max; decommissioning bond; net economic benefit finding and a community benefits agreement.Moratorium (Jan 28, 2025) expired Jan 26, 2026. Engie asked the CEC in late 2025 to pause its Compass opt-in review to study other sites. San Juan Capistrano (city) moratorium active per Carina.Opt-in: Compass Energy Storage (Engie, 250 MW/1,000 MWh, San Juan Capistrano), paused. CAISO queue: 2 active storage entries (405 MW), incl. Tyrell Energy Storage, Los Nietos.OC Development Services: BESS Facilities Ordinance 25-017 (Board adopted Nov 4, 2025)Nov 15, 2026
PlacerNo battery-specific rulesChapter 17 (Zoning) has no energy storage provisions (GoCodebook copy, Oct 2026 edition). Small solar plus storage goes through a Conditional Use Permit (Madena 4, PLN21-00411).None found in CEQAnet or news searches.Madena 4 Solar Energy and Battery Storage (5 MW AC) got a 2-year CUP extension Apr 23, 2026. CAISO queue: no storage entries.GoCodebook: Placer County Code, Oct 2026 editionCEQAnet: Madena 4Nov 15, 2026
PlumasNo battery-specific rulesTitle 9 (Planning and Zoning) has no energy storage provisions (GoCodebook copy, Oct 2026 edition).None found in CEQAnet or news searches.No BESS projects in CEQAnet since 2023. CAISO queue: no storage entries.GoCodebook: Plumas County Code, Oct 2026 editionNov 15, 2026
RiversideNo battery-specific rulesBESS approved within solar projects by Conditional Use Permit under Land Use Ordinance 348, Sec. 18.28 (Easley: 390 MW solar with up to 650 MW BESS). No BESS-specific code section found.None found.Desert Center cluster: Easley (Intersect Power), Sapphire Solar (117 MW with 117 MW BESS), Athos BESS siting (May 2025). CAISO queue: 17 active storage entries (5,586 MW); 17 completed.Riverside County Planning: Easley Renewable Energy Project agricultural preserve reportNov 15, 2026
SacramentoNo battery-specific rulesZoning Code has no energy storage provisions (GoCodebook copy, June 2026 edition). A shopping-center BESS enclosure went through a Special Development Permit and design review (AutoZone, Dec 2025).None found in CEQAnet or news searches.Dry Creek Energy Storage (30.1-acre BESS): state incidental take permit NOD Apr 14, 2026. SMUD started an EIR for its Twin Cities Solar and BESS May 27, 2026. Most projects sit in SMUD territory, outside the CAISO queue. CAISO queue: 1 active storage entry (59 MW), incl. Prospect Energy Storage.GoCodebook: Sacramento County Zoning Code, June 2026 editionCEQAnet: Dry Creek Energy StorageCEQAnet: SMUD Twin Cities Solar and BESSNov 15, 2026
San BenitoMoratoriumNo BESS rules in force; the moratorium bars accepting, processing or approving BESS applications in the unincorporated county. The draft Title 25 ordinance would exclude prime farmland, high fire hazard zones and 0.5-mile buffers around city spheres of influence, and ban NMC chemistry.45-day moratorium Mar 10, 2026 (4-1); renewed Apr 28; extended Jun 9, 2026 for up to 10 months 15 days (ends about late April 2027; exact date unconfirmed). Planning Commission continued the draft ordinance on Oct 20, 2026 to Dec 16, 2026.Allium Solar (Longroad Energy, 945-acre solar plus BESS off Hwy 156 near San Felipe Rd), the only BESS applicant. CAISO queue: 1 active storage entry (112 MW), incl. Allium Hybrid.BenitoLink: County planners again continue review of battery energy storage rules (Oct 26, 2026)Nov 15, 2026
San BernardinoNo battery-specific rulesStandalone BESS permitted as a Utility Facility by Conditional Use Permit (Zephyr Energy Storage, 40 MW/160 MWh, Planning Commission Mar 6, 2025). Development Code Ch. 84.29 regulates renewable generation; county policy RE 2.2 encourages storage paired with it.None found.Opt-in: Soda Mountain Solar (VC Renewables, 300 MW solar, 300 MW/1,200 MWh BESS), approved by the CEC Apr 2026. CAISO queue: 13 active storage entries (3,050 MW), incl. Baldy Mesa, Conduit Energy Storage, Roadhouse Storage; 6 completed.San Bernardino County Planning Commission agenda, Mar 6, 2025Nov 15, 2026
San DiegoDraft rulesNo BESS zoning standards adopted. County Fire interim guidelines (May 15, 2025) set 100 ft from residential, institutional and school buildings and 10 ft between enclosures. Board rejected a countywide moratorium in Sept 2024.Draft BESS Zoning Ordinance Amendment was out for public comment Aug 13 to Sept 27, 2026; Planning Commission and Board dates not posted.AES Seguro (Escondido area) drew the 2024 moratorium push. CAISO queue: 8 active storage entries (1,361 MW), incl. Desert Jewel Storage, East Field Energy Storage, Gateway Energy Storage 2; 14 completed.San Diego County PDS: Battery Energy Storage Systems ProjectNov 15, 2026
San FranciscoNo battery-specific rulesPlanning Code has no energy storage provisions; the building and fire codes cover lithium-ion battery charging and storage inside buildings (GoCodebook copy, Sept 2026 edition).None found in CEQAnet or news searches.CAISO queue: 1 active storage entry (250 MW), incl. Cormorant Storage.GoCodebook: San Francisco codes, Sept 2026 editionNov 15, 2026
San JoaquinNo battery-specific rulesDevelopment Title Sec. 9-901 lists battery storage facilities as a typical Utility Services, Major use, with no BESS-specific standards (GoCodebook copy, Oct 2026 edition). Projects use Site Approvals or Administrative Use Permits.None found in CEQAnet or news searches.Griffith Energy Storage (400 MW, Site Approval PA-2200137) approved Mar 12, 2024. A 40 MW/320 MWh BESS near Tracy (PA-2400335) approved July 11, 2025. The CEC approved the Potentia-Viridi opt-in BESS May 26, 2026; CAISO files it here and the CEC places it in Alameda County. CAISO queue: 8 active storage entries (2,001 MW), incl. Alta Casa Storage, Denali Energy Storage, Noosa Energy Storage, Pathfinder Storage; 3 completed.GoCodebook: San Joaquin Development Title, Sec. 9-901CEQAnet: Griffith Energy StorageCEQAnet: PA-2400335CEQAnet: Potentia-Viridi BESSNov 15, 2026
San Luis ObispoNo battery-specific rulesBESS reviewed by Conditional Use Permit under the energy-generating facilities rules (Title 22, Ch. 22.32), which a 2022 county briefing says allow them on non-prime agricultural land. Caballero (100 MW/400 MWh, Nipomo) got CUP DRC2019-00258.Residents asked the Board for a 2-year moratorium in Apr 2025; no county action found. City of Morro Bay moratorium runs to Jan 30, 2027 per Carina.Caballero operating since 2025. CAISO queue: 1 active storage entry (40 MW), incl. Cuyama Solar; 1 completed.CEQAnet: Caballero CA Storage CUP DRC2019-00258Nov 15, 2026
San MateoNo battery-specific rulesZoning Regulations have no energy storage provisions (GoCodebook copy, June 2026 edition).Data center moratorium (not BESS): interim urgency ordinance on the Nov 10, 2026 Board agenda; outcome not checked.No county BESS projects in CEQAnet since 2023. CAISO queue: 1 active storage entry (250 MW), incl. Baylands Battery.GoCodebook: San Mateo County Zoning Regulations, June 2026 editionNov 15, 2026
Santa BarbaraNo battery-specific rulesChapter 35 (Land Use and Development Code) and the Coastal Zoning Ordinance have no energy storage provisions; the county fire code sets ESS permit fees and a sprinkler exception (GoCodebook copy, Oct 2026 edition).None found in CEQAnet or news searches.Board took a BESS and Moss Landing report Mar 11, 2025 and backed SB 283 and AB 1285; EIR for the Imerys solar and BESS project under contract Aug 2025. CAISO queue: no storage entries.GoCodebook: Santa Barbara County Code, Oct 2026 editionNov 15, 2026
Santa ClaraNo battery-specific rulesAppendix I (Zoning) has no energy storage provisions; the county energy code requires battery pre-wiring in new homes (GoCodebook copy, Oct 2026 edition).None found in CEQAnet or news searches.The City of Santa Clara approved its Kifer Receiving Station BESS Aug 29, 2023. CAISO queue: 5 active storage entries (358 MW), incl. Kifer BESS 1, Los Esteros Critical Energy Facility Expansion, Milpa Power Bank, Tanager Storage; 1 completed.GoCodebook: Santa Clara County Code, Oct 2026 editionCEQAnet: Kifer Receiving Station BESSNov 15, 2026
Santa CruzDraft rulesNo BESS rules in force. Draft Energy Storage System Combining District (Sec. 13.10.408), approved as a draft by the Board Jan 13, 2026: sites of 10 acres or more next to transmission substations, with safety, farmland and environmental standards.County timeline shows CEQA review, then Planning Commission and Board hearings in fall 2026; no hearing date posted as of Nov 15, 2026.Opt-in: Seahawk BESS (New Leaf, sold to Invenergy; 200 MW/800 MWh at 90 Minto Rd near Watsonville; 26-OPT-02), under CEC review. Opposed by Stop Lithium BESS in Santa Cruz County. CAISO queue: 1 active storage entry (204 MW), incl. Seahawk Storage.Santa Cruz County: Battery Energy Storage Systems Ordinance pageNov 15, 2026
ShastaNo battery-specific rulesTitle 17 (Zoning) has no energy storage provisions (GoCodebook copy, Oct 2026 edition).None found in CEQAnet or news searches.Fountain Wind (205 MW wind) opt-in denied by the CEC Dec 19, 2025. CAISO queue: no storage entries.GoCodebook: Shasta County Code, Oct 2026 editionNov 15, 2026
SierraNo battery-specific rulesTitle 15 (Zoning) has no energy storage provisions (GoCodebook copy, Oct 2026 edition).None found in CEQAnet or news searches.No BESS projects in CEQAnet since 2023. CAISO queue: no storage entries.GoCodebook: Sierra County Code, Oct 2026 editionNov 15, 2026
SiskiyouNo battery-specific rulesTitle 10 (Planning and Zoning) has no energy storage provisions (GoCodebook copy, Oct 2026 edition).None found in CEQAnet or news searches.No BESS projects in CEQAnet since 2023. CAISO queue: no storage entries.GoCodebook: Siskiyou County Code, Oct 2026 editionNov 15, 2026
SolanoOrdinance in forceOrd. 2025-1864, Sec. 28.83 (effective Dec 4, 2025): front-of-meter BESS of 1 MWh or more needs a Use Permit heard by the Planning Commission and decided by the Board, and only in C-S, M-L, M-G-1/2, M-G-3, I-WD and I-AS zones. Banned in all agricultural, residential, marsh, watershed and park zones. No VHFHSZ sites; HFHSZ only in industrial zones. With thermal-runaway risk: 300 ft from sensitive receptors, 100 ft front, 50 ft side and rear. No indoor systems.Measure E (BESS tax of $1.50 per MWh of approved capacity per month, plus solar, wind, gas and data center taxes) trailed 37.6% yes to 62.3% no in KQED's Nov 13, 2026 count; certification is due by Dec 3, 2026. The CEC will recirculate the revised Corby staff assessment for 60 days (letter Oct 6, 2026). Corby is not on the Nov 18, 2026 business meeting agenda, and no decision date is set.Opt-in: Corby BESS (NextEra, 300 MW/1,200 MWh, ag land off Kilkenny Rd, under review); Vaca Dixon Power Center (157 MW/457 MWh, Vacaville city, application incomplete Feb 13, 2026). CAISO queue: 6 active storage entries (1,401 MW), incl. Corby, Corby 2, Tolenas, Arges BESS.Solano Ord. 2025-1864 as adopted Nov 4, 2025 (Legistar 25-905, PDF)Nov 15, 2026
SonomaNo battery-specific rulesChapter 26 (Zoning) has no energy storage provisions (GoCodebook copy, Oct 2026 edition). Borealis applied as a Public Utility Facility, which Sec. 26-30-100 allows in Land Extensive Agriculture with a use permit.Borealis Energy Storage (about 300 MW, 3571 Old Adobe Rd, Petaluma, PLP22-0025): EIR notice of preparation Oct 9, 2024; no hearing found. Bolero / North Bay Energy Storage (1901 Frates Rd, PLP22-0005): EIR peer review contract June 4, 2024.CAISO queue: 1 active storage entry (122 MW), incl. Wildhorse Energy Center.GoCodebook: Sonoma County Code, Oct 2026 editionCEQAnet: Borealis Energy StoragePermit Sonoma: Bolero project descriptionNov 15, 2026
StanislausNo battery-specific rulesTitle 21 (Zoning) has no energy storage provisions (GoCodebook copy, Oct 2026 edition). BESS goes through a Use Permit in General Agriculture (Saltgrass, A-2-40).Saltgrass Energy Storage (162 MW/650 MWh, PLN2025-0075) in early consultation since Jan 2, 2026. Amanece Hybrid Solar (400 MW, PLN2026-0068) entered early consultation Oct 22, 2026.TID and MID areas sit outside the CAISO queue. CAISO queue: 2 active storage entries (385 MW), incl. Crow Creek Solar 1, Golden Flats; 2 completed.GoCodebook: Stanislaus County Code, Oct 2026 editionCEQAnet: Saltgrass Energy StorageCEQAnet: Amanece Hybrid SolarNov 15, 2026
SutterNo battery-specific rulesZoning Code (Sec. 1500) has no energy storage provisions (GoCodebook copy, Oct 2026 edition).None found in CEQAnet or news searches.No BESS projects in CEQAnet since 2023. CAISO queue: 1 active storage entry (50 MW), incl. Township Power Bank.GoCodebook: Sutter County Code, Oct 2026 editionNov 15, 2026
TehamaNo battery-specific rulesTitle 17 (Zoning) has no energy storage provisions (GoCodebook copy, Oct 2026 edition).None found in CEQAnet or news searches.No county BESS projects in CEQAnet since 2023. CAISO queue: no storage entries.GoCodebook: Tehama County Code, Oct 2026 editionNov 15, 2026
TrinityNo battery-specific rulesTitle 17 (Zoning) has no energy storage provisions (GoCodebook copy, Oct 2026 edition).None found in CEQAnet or news searches.No county BESS projects in CEQAnet since 2023. CAISO queue: no storage entries.GoCodebook: Trinity County Code, Oct 2026 editionNov 15, 2026
TulareNo battery-specific rulesThe adopted Zoning Ordinance has no battery storage definition or use listing; BESS has gone through Special Use Permits in AE zones (Tulare 40 Generation Facility, PSP 23-012). Ordinance Code Part VII has no energy storage provisions (GoCodebook copy, Oct 2026 edition).A draft Zoning Ordinance update for the agricultural zones (redline titled as of July 31, 2025) adds a Battery Storage definition as new language but no battery storage row in the zone use tables, where Utility Scale Solar needs a PC permit in every agricultural zone. Hearing date not found.Tulare 40 Generation Facility (40 MW solar, up to 20 MW storage, PSP 23-012) approved Aug 27, 2025. CAISO queue: 5 active storage entries (1,111 MW), incl. Bobor Storage, Mineral King Solar, Rexford 2 Solar Farm, Sequoia; 3 completed.Tulare County: draft agricultural zones redlineGoCodebook: Tulare County Ordinance Code, Oct 2026 editionCEQAnet: Tulare 40 Generation FacilityNov 16, 2026
TuolumneNo battery-specific rulesZoning Code (Title 17) has no energy storage provisions (GoCodebook copy, July 2026 edition).None found in CEQAnet or news searches.CAISO queue: no active storage entries; 1 completed (Ultrapower Chinese Station BESS).GoCodebook: Tuolumne County Zoning Code, July 2026 editionNov 15, 2026
VenturaOrdinance in forceOrd. 4630 (Board approved May 21, 2024): grid-scale energy storage is a listed use. In AE, OS and RA zones it needs a Planning Commission CUP and all such projects share a 100-acre countywide cap (NCZO Sec. 8107-49.1); no acreage cap in M1, M2, M3 and IND zones.County page tracks how much of the 100-acre cap is left. City of Moorpark (not county) adopted a BESS zoning amendment per Carina.Shoals Energy Storage CUP (notice of exemption Dec 2024). CAISO queue: 4 active storage entries (1,926 MW), incl. Drifter, Goldback Solar Center, Rosa, Shoals.Ventura County RMA: Energy Storage (Ordinance No. 4630)Nov 15, 2026
YoloOrdinance in forceSec. 8-2.1105 (Ord. 681.236, effective Dec 22, 2022): storage over 2 MW needs a Minor Use Permit in A-N, A-X, A-I, commercial, industrial and PQP zones and is barred in A-C, A-R, residential and park zones; 600 kW to 2 MW needs Site Plan Review outside residential and park zones. Standards: zone setbacks and heights, 60 dBA at the property line of the nearest offsite home, 10 ft vegetation clearance, screening, a decommissioning plan and a removal fund or bond.None found in CEQAnet or news searches.Gibson Solar Farm (up to 20 MW AC, Use Permit ZF2020-0043): EIR addendum Apr 1, 2026. CAISO queue: no storage entries.GoCodebook: Yolo County Code Sec. 8-2.1105, Oct 2026 editionCEQAnet: Gibson Solar FarmNov 15, 2026
YubaNo battery-specific rulesTitle XI (Development Code) has no energy storage provisions (GoCodebook copy, Oct 2026 edition).None found in CEQAnet or news searches.No BESS projects in CEQAnet since 2023. CAISO queue: no storage entries.GoCodebook: Yuba County Code, Oct 2026 editionNov 15, 2026
First page of the Solano County sample brief

County briefs

A brief covers one county in depth: the rules in force, pending changes, every project proposed in the last five years, how the supervisors voted and the next hearing date. Every claim links to its source. Briefs cover battery storage and data center sites, and Stephen Lloyd writes each one.