Santa Clara County battery storage rules
Projects go through general utility, energy or use-permit rules.
- Key rules
- Appendix I (Zoning) has no energy storage provisions; the county energy code requires battery pre-wiring in new homes (GoCodebook copy, Oct 2026 edition).
- Pending action
- None found in CEQAnet or news searches.
- Projects
- The City of Santa Clara approved its Kifer Receiving Station BESS Aug 29, 2023. CAISO queue: 5 active storage entries (358 MW), incl. Kifer BESS 1, Los Esteros Critical Energy Facility Expansion, Milpa Power Bank, Tanager Storage; 1 completed.
- Sources
A brief on Santa Clara County
A brief covers the rules in force, pending changes, every project proposed in the last five years, how the supervisors voted and the next hearing date, with every claim sourced.
Research from public records, not legal advice. How this table is built.